Lawnswood Roundabout Update

7 minutes ago
2 min read

We have spoken to both the contractors and highways engineers this week, who have provided the following update.

The works have now been completed with the last of the snagging being completed this week.

Northern Power Grid (NPG) began work this week to repair a faulty underground electricity cable on the A660 southbound approach to the roundabout. These repairs are being completed under lane closures, which is the reason cones will still be in use for the rest of this week. This is unconnected to the roundabout works, but the repairs need to be carried out. We apologise for this work, but the underground cables need to be repaired urgently.


When the roundabout will be finished? The principal contractors work will be completed this week, with Northern PowerGrid (NPG) works continuing into Mid-December.

When the pedestrian and cycle lanes will be finished and usable?  Once the NPG works are completed the principal contractor will complete the footway and cycleway in the northern central reserve and in the northeast quarter near the old police station, this work should start in December and be completed in January. The exact date is subject to the NPG programme which we have requested details of.

Why were the traffic lights were not working this weekend (21 & 22 November) The Engineer attended site on Monday 23rd Nov to investigate and fixed the issue.

When will the lanes cease to be coned off and all lanes opened?  A nearside left turn lane closure (24/7) on the A660 Otley Road southbound approach will remain on for NPG works with other off peak lane closures being removed this week.  From 10th December to 14th December some off peak lane closures are required for our Street lighting contractor and the signs contractor for snagging repairs.   

 The speed limit signs are going up, when will all the signage be finished? And will there be signs where the bus lane starts? The white lining indicates that drivers should move into the right hand lane, but after 9.30am the bus lane is accessible to all cars-will there be signage to indicate this?   The first sign for the bus lane needs to be 30m in advance of the start of the tapper lines, which is before the traffic lights on the exit of A660 Otley Road south bound, two keep right arrows at 30m and 15m are also installed before the tapped line road markings. I will review if additional signs are needed after the Stage 3 Road Safety Audit has been completed.


 
 